The nine lines of G702
| Line | What goes in it | Example |
|---|---|---|
| 1 | Original contract sum | 240,000 |
| 2 | Net change by change orders | 8,000 |
| 3 | Contract sum to date | 248,000 |
| 4 | Total completed and stored to date | 124,000 |
| 5 | Retainage | 12,400 |
| 6 | Total earned less retainage | 111,600 |
| 7 | Less previous certificates for payment | 72,000 |
| 8 | Current payment due | 39,600 |
| 9 | Balance to finish, including retainage | 136,400 |
The columns of G703
| Col | What goes in it |
|---|---|
| A | Item number |
| B | Description of work |
| C | Scheduled value |
| D | Work completed in earlier applications |
| E | Work completed this period |
| F | Materials presently stored |
| G | Total completed and stored to date, with its percentage |
| H | Balance to finish |
| I | Retainage |
Before you send it
- Line 4 on G702 must match the total of column G on G703.
- Attach the lien waiver the GC asks for.
- Many GCs want it notarized. Check before the cutoff.
The forms are licensed by the AIA and bought from AIA Contract Documents. Our worksheet does the arithmetic so the numbers are right when you fill them in.