The three stages
- Request. You price the change and send it.
- Directive. The GC tells you to proceed before the price is agreed. Get that in writing and track time and material from the first hour.
- Change order. Both sides sign. It now changes the contract sum.
Pricing one
Labor at your full rate, then material, then your markup.
| Change order 003 | Amount |
|---|---|
| Labor, 14 hours at $95 | 1,330.00 |
| Material | 420.00 |
| Markup, 15% | 262.50 |
| Add six receptacles, conference room | 2,012.50 |
The log
One line per change, from the day it’s asked for.
- Number, date and who asked
- Description
- Price and days
- Status: pending, approved or rejected
- The pay application it was billed on
Mistakes that cost money
- Starting on a handshake.
- Missing the notice deadline in your contract. Many require written notice within days.