Change orders: how to write, price and track them

A change order is a written, signed change to the contract: what’s being added or removed, what it costs, and how many days it adds. Until it’s signed, the extra work is at your risk.

By Newlith  ·  Checked 27 Nov 2026
Must state
Scope, price and time
Signed
Before the work starts
Billed
As new lines on the pay app

The three stages

  • Request. You price the change and send it.
  • Directive. The GC tells you to proceed before the price is agreed. Get that in writing and track time and material from the first hour.
  • Change order. Both sides sign. It now changes the contract sum.

Pricing one

Labor at your full rate, then material, then your markup.

Change order 003Amount
Labor, 14 hours at $951,330.00
Material420.00
Markup, 15%262.50
Add six receptacles, conference room2,012.50

The log

One line per change, from the day it’s asked for.

  • Number, date and who asked
  • Description
  • Price and days
  • Status: pending, approved or rejected
  • The pay application it was billed on

Mistakes that cost money

  • Starting on a handshake.
  • Missing the notice deadline in your contract. Many require written notice within days.
Questions

What people ask next.

What’s the difference between a change order and a change directive?

A change order is agreed and signed by both sides. A directive tells you to proceed before the price is settled.

Can I bill a change order before it’s approved?

Usually not. Most GCs pay only approved changes.

Do change orders carry retainage?

Yes, at the contract rate unless the contract says otherwise.