Skip to content
See what we’d build
Guides  /  Mechanics liens

Mechanics liens for subcontractors

A mechanics lien is a claim against the property you improved, recorded when you aren’t paid for your labor or materials. For a subcontractor it usually runs in three steps, each with a deadline set by state law: a preliminary notice early in the job, a recorded lien after the work ends, and a lawsuit to enforce it.

By Newlith  ·  Checked 27 Nov 2026
Claim against
The property
Usual steps
Notice, lien, enforcement
Deadlines
Set by each state

What is a mechanics lien?

It’s a security interest in the real estate your work went into. Once it’s recorded, the owner can’t easily sell or refinance until the lien is paid, bonded off or released, which is why a recorded lien tends to get unpaid invoices looked at.

It works even though you have no contract with the owner. That’s the point: a sub who isn’t paid by the GC can still look to the property.

Public property usually can’t be liened. On public jobs you claim against the GC’s payment bond instead: the Miller Act on federal work, and each state’s own bond law on state and local work.

What is the usual sequence?

StepWhat you doWhen
1. NoticeServe a preliminary notice on the owner and others the state namesEarly in the job, in states that require one
2. LienRecord a claim of lien with the county where the property isWithin a set time after your work or the project ends
3. EnforceFile a lawsuit to foreclose the lienWithin a set time after the lien is recorded
4. ReleaseRecord a release once you’re paidAfter payment

Why do deadlines vary by state?

Every state writes its own lien statute, and the clocks start from different events: your last day of work, the project’s completion, or a notice the owner records. Three states and federal work, for a subcontractor on commercial work:

WhereRecord the lienEnforce it
CaliforniaThe earlier of 90 days after the project is complete, or 30 days after the owner records a notice of completion or cessationLawsuit within 90 days after recording
FloridaWithin 90 days after your final furnishing of labor or materialLawsuit within 1 year after recording, or 60 days if the owner serves a notice of contest
TexasBy the 15th day of the fourth month after the month the original contract was completed, terminated or abandonedLawsuit within 1 year after the last day you could have recorded
Federal (Miller Act bond, no lien)A sub to a sub gives notice to the prime within 90 days after its last workLawsuit within 1 year after your last work

These are summaries. Each state adds its own conditions, such as the notices that must come first, and they change when legislatures amend the law. Texas rewrote its lien deadlines with effect from 1 January 2022.

A worked example

A mechanical sub on a private job in Florida. It served its notice to owner on time. Its last day of work was 12 June 2026, and it’s still owed money.

ItemAmount
Subcontract290,000
Approved change orders20,000
Total earned310,000
Paid to date248,000
Owed62,000

Of the $62,000, $31,000 is retainage (10% of $310,000) and $31,000 is the last unpaid pay application. Both go on the lien.

The 90 day clock runs from 12 June: 18 days to the end of June, 31 in July and 31 in August make 80, so day 90 is 10 September 2026. If the lien is recorded on 20 August 2026, the lawsuit to enforce it is due by 20 August 2027, unless the owner serves a notice of contest and cuts that to 60 days.

How do liens relate to lien waivers?

A lien waiver gives up your lien rights for the amount it covers. You sign one with almost every payment, so the waivers you’ve signed decide what’s left to lien.

  • A conditional waiver takes effect only once the payment clears. An unconditional one takes effect when you sign it.
  • A waiver through a date covers all work to that date unless you list exceptions. List unpaid retainage and unpaid change orders.
  • A final unconditional waiver signed before the money arrives can leave you with nothing to lien.

Mistakes that cost money

  • Waiting on promises. The recording deadline keeps running while the GC says the check is coming.
  • Missing the notice at the start, which can cost the lien at the end.
  • Liening the wrong property or the wrong owner. Use the legal description and the owner of record.
  • Overstating the amount. Many states penalise a lien that knowingly claims more than is owed.
  • Recording the lien and stopping there. An unenforced lien expires when the enforcement deadline passes.

This is general information, not legal advice. Your contract and your state’s law decide.

Questions

What people ask next.

Can a subcontractor file a mechanics lien?

Yes. Subcontractors and suppliers are the people lien laws mostly protect, because they have no contract with the owner. Most states set conditions first, such as a preliminary notice.

How long do I have to file a mechanics lien?

It depends on the state. Florida allows 90 days after your final furnishing, while California and Texas count from the completion of the project, so check the law where the property is.

What happens after a mechanics lien is recorded?

The owner can pay, bond off the lien or dispute it. If none of that happens, you have to file a lawsuit to enforce the lien before the state’s deadline, or the lien expires.

Can I file a lien on a public project?

Usually not, because public property can’t be liened. Instead you claim against the payment bond, under the Miller Act on federal work or the state’s bond law on state and local work.

Can I lien for retainage?

Yes, unpaid retainage is money owed for work you’ve done. Watch the deadline, because retainage often comes due after the lien clock has started running.

Does a lien waiver end my lien rights?

Only for the amount and period it covers. A conditional waiver depends on the payment clearing, while an unconditional one takes effect when you sign it.