What is a mechanics lien?
It’s a security interest in the real estate your work went into. Once it’s recorded, the owner can’t easily sell or refinance until the lien is paid, bonded off or released, which is why a recorded lien tends to get unpaid invoices looked at.
It works even though you have no contract with the owner. That’s the point: a sub who isn’t paid by the GC can still look to the property.
Public property usually can’t be liened. On public jobs you claim against the GC’s payment bond instead: the Miller Act on federal work, and each state’s own bond law on state and local work.
What is the usual sequence?
| Step | What you do | When |
|---|---|---|
| 1. Notice | Serve a preliminary notice on the owner and others the state names | Early in the job, in states that require one |
| 2. Lien | Record a claim of lien with the county where the property is | Within a set time after your work or the project ends |
| 3. Enforce | File a lawsuit to foreclose the lien | Within a set time after the lien is recorded |
| 4. Release | Record a release once you’re paid | After payment |
Why do deadlines vary by state?
Every state writes its own lien statute, and the clocks start from different events: your last day of work, the project’s completion, or a notice the owner records. Three states and federal work, for a subcontractor on commercial work:
| Where | Record the lien | Enforce it |
|---|---|---|
| California | The earlier of 90 days after the project is complete, or 30 days after the owner records a notice of completion or cessation | Lawsuit within 90 days after recording |
| Florida | Within 90 days after your final furnishing of labor or material | Lawsuit within 1 year after recording, or 60 days if the owner serves a notice of contest |
| Texas | By the 15th day of the fourth month after the month the original contract was completed, terminated or abandoned | Lawsuit within 1 year after the last day you could have recorded |
| Federal (Miller Act bond, no lien) | A sub to a sub gives notice to the prime within 90 days after its last work | Lawsuit within 1 year after your last work |
These are summaries. Each state adds its own conditions, such as the notices that must come first, and they change when legislatures amend the law. Texas rewrote its lien deadlines with effect from 1 January 2022.
A worked example
A mechanical sub on a private job in Florida. It served its notice to owner on time. Its last day of work was 12 June 2026, and it’s still owed money.
| Item | Amount |
|---|---|
| Subcontract | 290,000 |
| Approved change orders | 20,000 |
| Total earned | 310,000 |
| Paid to date | 248,000 |
| Owed | 62,000 |
Of the $62,000, $31,000 is retainage (10% of $310,000) and $31,000 is the last unpaid pay application. Both go on the lien.
The 90 day clock runs from 12 June: 18 days to the end of June, 31 in July and 31 in August make 80, so day 90 is 10 September 2026. If the lien is recorded on 20 August 2026, the lawsuit to enforce it is due by 20 August 2027, unless the owner serves a notice of contest and cuts that to 60 days.
How do liens relate to lien waivers?
A lien waiver gives up your lien rights for the amount it covers. You sign one with almost every payment, so the waivers you’ve signed decide what’s left to lien.
- A conditional waiver takes effect only once the payment clears. An unconditional one takes effect when you sign it.
- A waiver through a date covers all work to that date unless you list exceptions. List unpaid retainage and unpaid change orders.
- A final unconditional waiver signed before the money arrives can leave you with nothing to lien.
Mistakes that cost money
- Waiting on promises. The recording deadline keeps running while the GC says the check is coming.
- Missing the notice at the start, which can cost the lien at the end.
- Liening the wrong property or the wrong owner. Use the legal description and the owner of record.
- Overstating the amount. Many states penalise a lien that knowingly claims more than is owed.
- Recording the lien and stopping there. An unenforced lien expires when the enforcement deadline passes.
This is general information, not legal advice. Your contract and your state’s law decide.