Skip to content
See what we’d build
Guides  /  Preliminary notice

Preliminary notice: what it is and when to send it

A preliminary notice is a letter a subcontractor or supplier sends early in a job to tell the owner, and often the GC and the lender, that it is working on the property and may claim a lien if it isn’t paid. Many states require one before you can file a lien, and each state sets its name, deadline and recipients.

By Newlith  ·  Checked 27 Nov 2026
Sent by
Subs and suppliers
Deadline
Set by state law
Miss it and
Lien rights can be lost

What is a preliminary notice?

It’s a notice that you’re on the job. The owner usually has no contract with you and may not know you exist, so the notice tells them who you are, who hired you and what you’re supplying.

In the states that require it, the notice is a condition of your lien rights. Send it late or to the wrong people and you can lose the right to file a lien for some or all of your work, even if you’re never paid.

Who sends it, and who gets it?

Subcontractors, sub subcontractors and suppliers send it, because they have no contract with the owner. A GC with a direct contract usually doesn’t need one, though California asks a direct contractor to give notice to the construction lender if there is one.

  • The owner of the property, named as the records show it, which may not be the tenant who ordered the work.
  • The GC or direct contractor.
  • The construction lender, where the state requires it and there is one.
  • In some states, the party you contracted with, if that isn’t the GC.

In California the direct contractor has to give you the owner’s and lender’s names and addresses when you ask, so ask on day one.

Why do the name and deadline change by state?

Each state writes its own lien law, so each state decides whether a notice is needed, what it’s called, when it’s due and who must get it. Four examples for private commercial work:

StateNameDueSent to
CaliforniaPreliminary notice, the 20 day notice20 days after you first furnish workOwner, direct contractor, lender
ArizonaPreliminary twenty day lien notice20 days after you first furnish workOwner, lender, the party you contracted with
FloridaNotice to owner45 days after you start workOwner
TexasNotice of claim for unpaid labor or materials15th day of the third month after the month of the unpaid workOwner and original contractor

In California and Arizona a late notice still counts, but it only covers work from the 20 days before you served it onward. Texas works differently: its notice is about nonpayment, so it’s sent for each month that goes unpaid rather than once at the start. Some states have no preliminary notice for some or all claimants, and public jobs usually follow separate bond rules.

A worked example

An electrical sub on a private office job in California, first on site on 3 March, serves its preliminary notice on 30 March.

DateWhat happens
3 MarchFirst day on site. The 20 day clock starts.
23 MarchDeadline for a notice that covers all the work.
30 MarchNotice served, 7 days late.
ResultLien rights cover work from 10 March, which is 30 March less 20 days.

The work done from 3 to 9 March, say $14,200 of rough in labor and material, falls outside the notice. If the job goes unpaid, that $14,200 can’t go on the lien. Serving by 23 March would have covered it.

How to track it per job

  • One line per job: the state, the first day you furnished labor or material, and the deadline that date gives you.
  • Who must be served, with names and addresses taken from the records or from the GC, not from the bid invite.
  • The date served, how it was sent and where the proof of mailing is kept.
  • Send one on every job in a notice state, by default. It’s a routine step, not a threat.
  • A new supplier or a new tier under you can mean a new notice. Check when the job changes.

Mistakes that cost money

  • Counting from the contract date. The clock usually runs from the first day you furnish labor or material, which may be a delivery.
  • Naming the tenant or the developer instead of the property owner of record.
  • Sending it the wrong way. Some states name the delivery method, and without proof of mailing the notice can be hard to prove.
  • Skipping it because you know the GC. The notice protects you if the owner doesn’t pay the GC, which is outside both your control.
  • Using one state’s rules in another. Check the state the property is in, not the state your shop is in.

This is general information, not legal advice. Your contract and your state’s law decide.

Questions

What people ask next.

Is a preliminary notice the same as a lien?

No. A preliminary notice only tells the owner you’re working on the property. A lien is a separate claim you record later if you aren’t paid.

Does sending a preliminary notice mean I expect not to be paid?

No. In states that require it, the notice is a routine step that keeps your lien rights open. Many subs send one on every job.

What is a 20 day notice?

It’s the common name for the preliminary notice in California and Arizona, where it’s due 20 days after you first furnish labor or material. A late notice covers only the work from 20 days before it was served onward.

What is a notice to owner?

It’s Florida’s name for its preliminary notice. It’s due within 45 days after you start work on the job and it’s served on the owner.

Do I need a preliminary notice on a public job?

Public property usually can’t be liened, so public jobs use claims against a payment bond instead. Those claims have their own notice rules and deadlines, set by federal or state law.

Do suppliers send preliminary notices?

Usually, yes. Where a state requires the notice, suppliers to a subcontractor are generally among the claimants who must send it to keep their lien rights.