Guides  /  Schedule of values

Schedule of values

A schedule of values breaks a contract’s total price into line items, each with a dollar value. It’s the basis of every pay application: each month you bill a percentage of each line.

By Newlith  ·  Checked 27 Nov 2026
Adds up to
The full contract sum
Submitted
Before the first pay app
Lives on
AIA G703 or the GC’s form

How to build one

  • Follow how the work gets done: by phase, area or system.
  • Give mobilization, submittals and closeout their own lines.
  • Keep each line small enough that a percentage is easy to defend on site.
  • Don’t load the early lines. An overbilled first line is the fastest way to get a pay app sent back.

An example

A $240,000 electrical subcontract.

ItemDescriptionValue
1Mobilization and submittals12,000
2Underground and slab rough in28,000
3Branch rough in52,000
4Feeders and switchgear46,000
5Lighting fixtures38,000
6Devices and trim30,000
7Fire alarm22,000
8Testing and closeout12,000
Contract sum240,000

Where change orders go

Approved change orders are added at the bottom as new lines. The original lines stay as they were approved.

Questions

What people ask next.

Who approves a schedule of values?

The GC, and often the architect, before your first pay application.

Can I change it mid job?

Only with approval. Changes normally come through change orders.

How many lines should it have?

There’s no rule. Each line should be something a person can walk the site and judge.