How to build one
- Follow how the work gets done: by phase, area or system.
- Give mobilization, submittals and closeout their own lines.
- Keep each line small enough that a percentage is easy to defend on site.
- Don’t load the early lines. An overbilled first line is the fastest way to get a pay app sent back.
An example
A $240,000 electrical subcontract.
| Item | Description | Value |
|---|---|---|
| 1 | Mobilization and submittals | 12,000 |
| 2 | Underground and slab rough in | 28,000 |
| 3 | Branch rough in | 52,000 |
| 4 | Feeders and switchgear | 46,000 |
| 5 | Lighting fixtures | 38,000 |
| 6 | Devices and trim | 30,000 |
| 7 | Fire alarm | 22,000 |
| 8 | Testing and closeout | 12,000 |
| Contract sum | 240,000 |
Where change orders go
Approved change orders are added at the bottom as new lines. The original lines stay as they were approved.