How is retainage worked out?
Retainage is a percent of each progress payment that the owner or general contractor holds until the work is done. On each pay application you multiply this period’s billing by the rate, subtract it from the billing, and add it to what is already held.
payment due = billed this period − held this period
held to date = held before + held this period
These are the same steps as lines 4 to 8 of the AIA G702, where retainage is taken on work completed and materials stored. The G702 and G703 guide walks through every line.
A worked example
A $240,000.00 subcontract with 10% retainage, and a contract that cuts the rate to 5% on billing past the halfway point, $120,000.00. It is billed over four pay applications.
| Pay app | Billed | Held | Paid | Held to date |
|---|---|---|---|---|
| 1 | $48,000.00 | $4,800.00 | $43,200.00 | $4,800.00 |
| 2 | $48,000.00 | $4,800.00 | $43,200.00 | $9,600.00 |
| 3 | $72,000.00 | $4,800.00 | $67,200.00 | $14,400.00 |
| 4 | $72,000.00 | $3,600.00 | $68,400.00 | $18,000.00 |
Pay application 3 crosses the halfway line. $24,000.00 of it is held at 10% and $48,000.00 at 5%, so $4,800.00 is held and $67,200.00 is due.
By the end $222,000.00 has been paid and $18,000.00 is held, still to bill. At a flat 10% the same job would hold $24,000.00.
When does the rate drop?
It depends on the contract and, on public work, on state law. Some states cut the rate once a public job is 50% complete, some stop retainage at that point, and some cap it for the whole job. Private contracts set their own terms.
Contracts also differ on how the cut works. This calculator applies the lower rate to billing past the halfway point and releases nothing already held. If your contract instead releases part of what is held, work that step from the contract’s own wording.
How is retainage released?
Usually at substantial or final completion, as the contract says, and a subcontractor is often paid after the owner releases it to the general contractor. It rarely arrives on its own: bill it on a final pay application. The retainage guide covers how to track it job by job.
This is general information, not legal advice. Your contract and state law decide.