Retainage calculator

What’s held this period and to date, what’s due, and what’s still to bill.

Include approved change orders.

Work completed and materials stored this period.

Total on earlier pay applications. Leave blank on the first one.

Optional. Only if your contract or state law cuts the rate at the halfway point. Enter 0 if it stops.

This pay application
$64,800.00

Payment due this period, after $7,200.00 held.

Retainage held this period
$7,200.00
Retainage held to date
$16,800.00
Payment due this period
$64,800.00
Retainage still to bill
$16,800.00
Contract left to bill
$72,000.00
How it’s worked outbilled to date = $96,000.00 + $72,000.00 = $168,000.00held this period = $72,000.00 × 10% = $7,200.00held to date = $9,600.00 + $7,200.00 = $16,800.00payment due = $72,000.00 − $7,200.00 = $64,800.00
  • Retainage still to bill is everything held to date. It is billed when the contract releases it.
  • Balance to finish, retainage included: $88,800.00

This tool is a check. Your contract and state law decide the rate and when it’s released.

How is retainage worked out?

Retainage is a percent of each progress payment that the owner or general contractor holds until the work is done. On each pay application you multiply this period’s billing by the rate, subtract it from the billing, and add it to what is already held.

held this period = billed this period × rate
payment due = billed this period − held this period
held to date = held before + held this period

These are the same steps as lines 4 to 8 of the AIA G702, where retainage is taken on work completed and materials stored. The G702 and G703 guide walks through every line.

A worked example

A $240,000.00 subcontract with 10% retainage, and a contract that cuts the rate to 5% on billing past the halfway point, $120,000.00. It is billed over four pay applications.

Pay appBilledHeldPaidHeld to date
1$48,000.00$4,800.00$43,200.00$4,800.00
2$48,000.00$4,800.00$43,200.00$9,600.00
3$72,000.00$4,800.00$67,200.00$14,400.00
4$72,000.00$3,600.00$68,400.00$18,000.00

Pay application 3 crosses the halfway line. $24,000.00 of it is held at 10% and $48,000.00 at 5%, so $4,800.00 is held and $67,200.00 is due.

By the end $222,000.00 has been paid and $18,000.00 is held, still to bill. At a flat 10% the same job would hold $24,000.00.

When does the rate drop?

It depends on the contract and, on public work, on state law. Some states cut the rate once a public job is 50% complete, some stop retainage at that point, and some cap it for the whole job. Private contracts set their own terms.

Contracts also differ on how the cut works. This calculator applies the lower rate to billing past the halfway point and releases nothing already held. If your contract instead releases part of what is held, work that step from the contract’s own wording.

How is retainage released?

Usually at substantial or final completion, as the contract says, and a subcontractor is often paid after the owner releases it to the general contractor. It rarely arrives on its own: bill it on a final pay application. The retainage guide covers how to track it job by job.

This is general information, not legal advice. Your contract and state law decide.

01  Questions

What people ask next.

How do you calculate retainage on a pay application?

Multiply the work completed and materials stored this period by the retainage rate. The payment due is this period’s billing less that amount, and the total held so far is carried to the next application.

Is retainage taken on stored materials?

Usually yes, because the AIA G702 applies retainage to work completed and to materials stored. Some contracts set a different rate for stored materials, so check yours.

What is a typical retainage rate?

Five to ten percent of each progress payment is common. Many states cap the rate on public work, and the cap and any reduction vary by state, so the contract and the statute decide.

Does retainage drop once the job is half done?

Sometimes. Some state laws for public jobs and some contracts cut the rate, or stop holding it, once the work is 50% complete. Others make no change until completion.

Is retainage still to bill part of the balance to finish?

Yes. On the AIA G702, the balance to finish includes retainage, because money held has been earned but not paid. You bill it when the contract releases it.

Are change orders subject to retainage?

Usually, at the contract rate, unless the contract says otherwise. Add approved change orders to the contract value before you run the numbers.