What is in a closeout package?
The list for your job is in the specs. Division 01 usually carries it in sections such as 01 77 00 Closeout Procedures, 01 78 23 Operation and Maintenance Data, 01 78 39 Project Record Documents and 01 78 46 Extra Stock Materials, and each trade section adds its own items. Numbering varies by owner and design firm, so read the project’s own set.
- O&M manuals: the manufacturer’s operating and maintenance instructions, parts lists and service contacts for what you installed.
- As built drawings, also called record drawings: your marked up set showing where things really went.
- Warranties: the manufacturers’ warranties and your own written warranty on the work.
- Test and inspection reports: start up reports, test results and signed off inspections.
- Attic stock: the spare material the specs require you to leave, such as extra sprinkler heads, filters or fixtures.
- Final lien waiver, plus whatever affidavits or releases the contract asks for.
A closeout checklist
One line per item, started the day the job is awarded, not the day the punch list closes.
| Item | Where it’s specified | Who signs or supplies | Status |
|---|---|---|---|
| O&M manuals, one per system | 01 78 23 and trade sections | Manufacturers, assembled by you | Draft sent |
| As built drawings | 01 78 39 | Your foreman’s marked up set | In progress |
| Warranties | Trade sections | You and each manufacturer | Collected |
| Test and start up reports | Trade sections | You or the manufacturer’s technician | Two of three |
| Inspection sign offs | Permit and local code | The inspector | Final passed |
| Attic stock, with a signed receipt | 01 78 46 and trade sections | Owner’s representative signs | Not delivered |
| Owner training record | Trade sections | Owner’s staff sign | Booked |
| Final lien waiver | Subcontract | You | With final pay app |
Documents your trade adds
The trade sections of the specs add their own records. A few common ones:
- Fire sprinkler: the contractor’s material and test certificate for aboveground piping, the form published with NFPA 13, signed by you and the owner’s representative.
- Fire alarm: the NFPA 72 record of completion, filled out by the installing contractor and given to the owner and the authority having jurisdiction.
- Electrical: panel schedules updated to match the as builts, and the test reports the specs call for.
- Mechanical: start up reports for each unit and the control sequences as installed.
Your local authority having jurisdiction may use its own version of these forms. Use the one it asks for.
How does closeout tie to retainage?
Under the AIA’s general conditions, A201, the GC’s final payment from the owner waits on an affidavit that bills are paid, the surety’s consent where there’s a bond, releases or waivers of liens, and the other documents the contract requires. The GC passes those conditions down, so its subs’ closeout packages have to be in before it can collect, and your retainage usually follows the owner’s release.
A201 also starts the warranties it requires at substantial completion, unless the certificate of substantial completion says otherwise, and gives a one year correction period from that date. Note the date on your warranty letters.
A worked example
A $480,000 mechanical subcontract with 10% retainage. The punch list is closed and the last progress billing is paid. What’s still owed:
| Item | Amount |
|---|---|
| Retainage on the base contract, 10% of 480,000 | 48,000.00 |
| Retainage on approved change orders, 10% of 36,500 | 3,650.00 |
| Held until closeout is accepted | 51,650.00 |
If the O&M manuals and attic stock receipt are missing, the whole $51,650 can sit while the GC waits for them. Bill the retainage on its own pay application with the closeout package attached, so nothing is left for anyone to chase.
Mistakes that cost money
- Starting closeout after the punch list. Collect warranties and cut sheets when you buy the equipment.
- Letting the foreman’s marked up set go missing. As builts can’t be drawn from memory.
- Dropping off attic stock without a signed receipt, then being asked for it again.
- Signing an unconditional final waiver before the money has cleared.
- Forgetting a lien deadline while you wait for closeout to be accepted. In many states the clock runs from your last day of work.
See the lien waivers guide for which waiver to sign at the end of a job.
This is general information, not legal advice. Your contract and state law decide.