Project closeout documents

Closeout documents are the package a subcontractor hands over at the end of a job: O&M manuals, as built drawings, warranties, test and inspection reports, attic stock and a final lien waiver. Final payment and retainage usually wait on this package, so a late or incomplete one keeps your own money held.

By Newlith  ·  Checked 27 Nov 2026
Due
At the end of the job
Listed in
The Division 01 closeout specs
Releases
Final payment and retainage

What is in a closeout package?

The list for your job is in the specs. Division 01 usually carries it in sections such as 01 77 00 Closeout Procedures, 01 78 23 Operation and Maintenance Data, 01 78 39 Project Record Documents and 01 78 46 Extra Stock Materials, and each trade section adds its own items. Numbering varies by owner and design firm, so read the project’s own set.

  • O&M manuals: the manufacturer’s operating and maintenance instructions, parts lists and service contacts for what you installed.
  • As built drawings, also called record drawings: your marked up set showing where things really went.
  • Warranties: the manufacturers’ warranties and your own written warranty on the work.
  • Test and inspection reports: start up reports, test results and signed off inspections.
  • Attic stock: the spare material the specs require you to leave, such as extra sprinkler heads, filters or fixtures.
  • Final lien waiver, plus whatever affidavits or releases the contract asks for.

A closeout checklist

One line per item, started the day the job is awarded, not the day the punch list closes.

ItemWhere it’s specifiedWho signs or suppliesStatus
O&M manuals, one per system01 78 23 and trade sectionsManufacturers, assembled by youDraft sent
As built drawings01 78 39Your foreman’s marked up setIn progress
WarrantiesTrade sectionsYou and each manufacturerCollected
Test and start up reportsTrade sectionsYou or the manufacturer’s technicianTwo of three
Inspection sign offsPermit and local codeThe inspectorFinal passed
Attic stock, with a signed receipt01 78 46 and trade sectionsOwner’s representative signsNot delivered
Owner training recordTrade sectionsOwner’s staff signBooked
Final lien waiverSubcontractYouWith final pay app

Documents your trade adds

The trade sections of the specs add their own records. A few common ones:

  • Fire sprinkler: the contractor’s material and test certificate for aboveground piping, the form published with NFPA 13, signed by you and the owner’s representative.
  • Fire alarm: the NFPA 72 record of completion, filled out by the installing contractor and given to the owner and the authority having jurisdiction.
  • Electrical: panel schedules updated to match the as builts, and the test reports the specs call for.
  • Mechanical: start up reports for each unit and the control sequences as installed.

Your local authority having jurisdiction may use its own version of these forms. Use the one it asks for.

How does closeout tie to retainage?

Under the AIA’s general conditions, A201, the GC’s final payment from the owner waits on an affidavit that bills are paid, the surety’s consent where there’s a bond, releases or waivers of liens, and the other documents the contract requires. The GC passes those conditions down, so its subs’ closeout packages have to be in before it can collect, and your retainage usually follows the owner’s release.

A201 also starts the warranties it requires at substantial completion, unless the certificate of substantial completion says otherwise, and gives a one year correction period from that date. Note the date on your warranty letters.

A worked example

A $480,000 mechanical subcontract with 10% retainage. The punch list is closed and the last progress billing is paid. What’s still owed:

ItemAmount
Retainage on the base contract, 10% of 480,00048,000.00
Retainage on approved change orders, 10% of 36,5003,650.00
Held until closeout is accepted51,650.00

If the O&M manuals and attic stock receipt are missing, the whole $51,650 can sit while the GC waits for them. Bill the retainage on its own pay application with the closeout package attached, so nothing is left for anyone to chase.

Mistakes that cost money

  • Starting closeout after the punch list. Collect warranties and cut sheets when you buy the equipment.
  • Letting the foreman’s marked up set go missing. As builts can’t be drawn from memory.
  • Dropping off attic stock without a signed receipt, then being asked for it again.
  • Signing an unconditional final waiver before the money has cleared.
  • Forgetting a lien deadline while you wait for closeout to be accepted. In many states the clock runs from your last day of work.

See the lien waivers guide for which waiver to sign at the end of a job.

This is general information, not legal advice. Your contract and state law decide.

Questions

What people ask next.

What are closeout documents in construction?

They are the records a contractor hands over at the end of a job so the owner can run and maintain the building. They usually include O&M manuals, as built drawings, warranties, test reports, attic stock and final lien waivers.

What is attic stock?

Attic stock is spare material the specs require you to leave with the owner, such as extra sprinkler heads, filters or light fixtures. The specs set the quantities, and a signed receipt proves you delivered it.

What is the difference between as built drawings and record drawings?

Many specs use the two names for the same thing: the contractor’s marked up drawings showing what was really installed. Some firms use record drawings for the set the architect produces from those markups.

When does the warranty period start?

Under AIA A201, warranties required by the contract start at substantial completion unless the certificate of substantial completion says otherwise. Your subcontract can set a different date, so check it.

Can a GC hold my retainage until closeout documents are in?

Often yes, because most subcontracts make complete closeout a condition of final payment. State prompt payment and retainage laws can limit how long it can be held, and they vary.

Which lien waiver do I send at closeout?

Usually a conditional final waiver with your final pay application, then an unconditional final waiver once the payment has cleared. Some states require their own statutory forms.