Pay when paid versus pay if paid

A pay when paid clause sets when the GC pays you: after the owner pays the GC, or within a reasonable time if the owner never does. A pay if paid clause makes the owner’s payment a condition, so if the owner never pays, the GC doesn’t either. States treat the two very differently, and some refuse to enforce pay if paid at all.

By Newlith  ·  Checked 27 Nov 2026
Pay when paid
Sets the timing
Pay if paid
Moves the risk to you
Enforced
Varies by state

What is the difference?

Both clauses tie your payment to the owner paying the GC. The difference shows up only when the owner doesn’t pay at all.

ClauseOwner pays the GC lateOwner never pays the GC
Pay when paidYou’re paid a set time after the GC is paidThe GC still owes you, within a reasonable time
Pay if paidYou’re paid a set time after the GC is paidThe GC may owe you nothing, where the clause is enforced

The classic reading of pay when paid comes from a 1962 federal appeals case, Thos. J. Dyer Co. v. Bishop International Engineering, which treated the clause as a timing rule and not a reason never to pay the sub.

How do you tell them apart in a subcontract?

By the words. Courts in most states read the clause as pay when paid unless it says plainly that the owner’s payment is a condition.

  • Pay if paid wording: “condition precedent”, “only if and to the extent that the contractor is paid”, “the subcontractor assumes the risk of the owner’s nonpayment”.
  • Pay when paid wording: “within 7 days after the contractor receives payment”, with nothing that makes the owner’s payment a condition.
  • Watch for both in one clause. A timing sentence followed by a risk sentence is still a pay if paid clause.

How do courts in different states treat them?

It varies a great deal. Five examples:

StatePay if paidSource
CaliforniaVoid as against public policyWm. R. Clarke Corp. v. Safeco, 1997
New YorkVoid as against public policyWest-Fair Electric Contractors v. Aetna, 1995
North CarolinaUnenforceable: owner payment is not a condition of paying the subN.C. Gen. Stat. 22C-2
FloridaEnforced if the clause clearly makes owner payment a condition. If it’s unclear, it’s read as pay when paidFlorida case law
TexasAllowed with limits, for example where the owner’s nonpayment is the GC’s fault, and the sub can give written notice objectingTex. Bus. & Com. Code ch. 56

Other states have their own rules, and some have changed them recently. Check the law of the state the project is in, and the law the subcontract says governs it.

A worked example

A fire protection sub bills $86,000 on pay application 5, with 10% retainage held.

ItemAmount
Billed this period86,000
Retainage at 10%8,600
Due this period77,400

The subcontract says the GC pays within 10 days after it receives the owner’s payment. The owner pays the GC 60 days after the pay application, so under either clause the sub is paid around day 70.

Now the owner runs out of money and never pays. Under a pay when paid clause, the GC still owes the $77,400 within a reasonable time. Under a clearly worded pay if paid clause in a state that enforces it, the GC may owe nothing, and the sub’s best route to the $77,400 is a lien or a bond claim, if its notices are in order.

What to look for in a subcontract

  • Whether the clause says “condition precedent” or puts the risk of owner nonpayment on you.
  • A time limit. If you accept pay when paid, ask for an outside date, such as payment within a set number of days whatever happens.
  • Which state’s law governs the subcontract, and where disputes are heard.
  • Whether the GC must tell you when it’s paid, and pursue the owner if it isn’t.
  • Whether the clause tries to cover change orders and retainage too.

Mistakes that cost money

  • Signing a pay if paid clause without asking for a change. It is often negotiable before the subcontract is signed.
  • Relying on the clause being void. That’s true in some states and not others.
  • Letting lien and bond deadlines pass while you wait for the owner to pay the GC. Your notices protect you if the clause holds.
  • Assuming a pay if paid clause can’t affect a bond claim. Whether a surety can use it varies by state.

This is general information, not legal advice. Your contract and your state’s law decide.

Questions

What people ask next.

Is pay when paid the same as pay if paid?

No. Pay when paid sets the timing of your payment, while pay if paid makes the owner’s payment a condition of it. The difference matters when the owner never pays.

Are pay if paid clauses legal?

It depends on the state. California and New York courts have held them void, North Carolina’s statute makes them unenforceable, and states such as Florida enforce them when the wording is clear.

How long can a GC wait under a pay when paid clause?

If the owner pays, the clause sets the time, such as 7 or 10 days after receipt. If the owner never pays, courts in many states say the GC must pay within a reasonable time.

What makes a clause pay if paid?

Clear words that the owner’s payment is a condition precedent, or that you take the risk of the owner not paying. Without them, most courts read the clause as pay when paid.

Can I still file a lien under a pay if paid clause?

Often yes, because a lien is a claim against the property and not against the GC. Your preliminary notices and lien deadlines still apply, so keep them up to date.

Does prompt payment law override these clauses?

Many states have prompt payment laws that set deadlines for paying subs once the GC is paid. How they interact with a pay if paid clause depends on the state.