What is the difference?
Both clauses tie your payment to the owner paying the GC. The difference shows up only when the owner doesn’t pay at all.
| Clause | Owner pays the GC late | Owner never pays the GC |
|---|---|---|
| Pay when paid | You’re paid a set time after the GC is paid | The GC still owes you, within a reasonable time |
| Pay if paid | You’re paid a set time after the GC is paid | The GC may owe you nothing, where the clause is enforced |
The classic reading of pay when paid comes from a 1962 federal appeals case, Thos. J. Dyer Co. v. Bishop International Engineering, which treated the clause as a timing rule and not a reason never to pay the sub.
How do you tell them apart in a subcontract?
By the words. Courts in most states read the clause as pay when paid unless it says plainly that the owner’s payment is a condition.
- Pay if paid wording: “condition precedent”, “only if and to the extent that the contractor is paid”, “the subcontractor assumes the risk of the owner’s nonpayment”.
- Pay when paid wording: “within 7 days after the contractor receives payment”, with nothing that makes the owner’s payment a condition.
- Watch for both in one clause. A timing sentence followed by a risk sentence is still a pay if paid clause.
How do courts in different states treat them?
It varies a great deal. Five examples:
| State | Pay if paid | Source |
|---|---|---|
| California | Void as against public policy | Wm. R. Clarke Corp. v. Safeco, 1997 |
| New York | Void as against public policy | West-Fair Electric Contractors v. Aetna, 1995 |
| North Carolina | Unenforceable: owner payment is not a condition of paying the sub | N.C. Gen. Stat. 22C-2 |
| Florida | Enforced if the clause clearly makes owner payment a condition. If it’s unclear, it’s read as pay when paid | Florida case law |
| Texas | Allowed with limits, for example where the owner’s nonpayment is the GC’s fault, and the sub can give written notice objecting | Tex. Bus. & Com. Code ch. 56 |
Other states have their own rules, and some have changed them recently. Check the law of the state the project is in, and the law the subcontract says governs it.
A worked example
A fire protection sub bills $86,000 on pay application 5, with 10% retainage held.
| Item | Amount |
|---|---|
| Billed this period | 86,000 |
| Retainage at 10% | 8,600 |
| Due this period | 77,400 |
The subcontract says the GC pays within 10 days after it receives the owner’s payment. The owner pays the GC 60 days after the pay application, so under either clause the sub is paid around day 70.
Now the owner runs out of money and never pays. Under a pay when paid clause, the GC still owes the $77,400 within a reasonable time. Under a clearly worded pay if paid clause in a state that enforces it, the GC may owe nothing, and the sub’s best route to the $77,400 is a lien or a bond claim, if its notices are in order.
What to look for in a subcontract
- Whether the clause says “condition precedent” or puts the risk of owner nonpayment on you.
- A time limit. If you accept pay when paid, ask for an outside date, such as payment within a set number of days whatever happens.
- Which state’s law governs the subcontract, and where disputes are heard.
- Whether the GC must tell you when it’s paid, and pursue the owner if it isn’t.
- Whether the clause tries to cover change orders and retainage too.
Mistakes that cost money
- Signing a pay if paid clause without asking for a change. It is often negotiable before the subcontract is signed.
- Relying on the clause being void. That’s true in some states and not others.
- Letting lien and bond deadlines pass while you wait for the owner to pay the GC. Your notices protect you if the clause holds.
- Assuming a pay if paid clause can’t affect a bond claim. Whether a surety can use it varies by state.
This is general information, not legal advice. Your contract and your state’s law decide.