Billing for stored materials on a pay application

Stored materials are materials you’ve bought and delivered to the site or an approved warehouse but haven’t installed yet. On the AIA G703 continuation sheet they go in column F, materials presently stored. Most GCs pay for them only with proof: an invoice or bill of sale, insurance, photos and where the material is kept.

By Newlith  ·  Checked 27 Nov 2026
G703 column
F, materials presently stored
Adds into
Column G, D + E + F
Stored off site
Approval first

What counts as stored materials?

Material bought for the job and not yet part of the work. For an electrical, mechanical or fire protection sub that’s usually the large, long lead items: switchgear, panels, light fixtures, air handlers, chillers, pipe and fittings, sprinkler heads.

Billing for them matters because you pay the supplier long before the item is set. Without a stored materials line, that cash sits with you until installation, sometimes for months.

Where do they go on the G703?

In column F. The continuation sheet has one row per line of the schedule of values, and these columns:

ColumnHeadingHow it’s worked out
AItem numberFrom the schedule of values
BDescription of workFrom the schedule of values
CScheduled valueFrom the schedule of values
DWork completed, from previous applicationD + E from the last application
EWork completed, this periodInstalled this period
FMaterials presently storedStored now, not in D or E
GTotal completed and stored to dateD + E + F
%Percent completeG ÷ C
HBalance to finishC − G
IRetainageUsed if the rate varies by line

Column F is a snapshot of what’s stored now, so it isn’t carried forward from the last application. On the G702 summary page, retainage on stored material has its own line, 5b, worked out on the column F total, because some contracts hold a different rate on stored material.

What does a GC usually ask for?

The owner is paying for something that isn’t in the building yet, so the GC wants to know it exists, who owns it and that it’s protected.

  • The supplier’s invoice, or a bill of sale that passes title to the owner.
  • A certificate of insurance that covers the material where it’s stored and on the way to site.
  • Dated photos of the material, tagged with the job name.
  • The storage location: on site in a secure area, or the address of the warehouse.
  • For material stored off site, the owner’s approval in advance. AIA A201 section 9.3.2 makes this a condition, with procedures for title, insurance, storage and transport.

Some contracts add more, such as storage in a bonded warehouse, a right to inspect, or a supplier lien waiver. Read the payment section of the subcontract and the prime contract’s terms that flow down to you.

A worked example

An electrical sub has a $180,000 line for switchgear and distribution, with 10% retainage. On pay application 3 it bills $18,000 of conduit rough in and $62,000 of switchgear delivered to a locked room on site. On pay application 4 the gear is set, and it bills $20,000 more labor.

ColumnPay app 3Pay app 4
C Scheduled value180,000180,000
D Previous018,000
E This period18,00082,000
F Stored62,0000
G Total to date80,000100,000
% Complete44.4%55.6%
H Balance100,00080,000
Retainage at 10%8,00010,000

On pay application 4, the $62,000 of gear leaves column F and goes into column E with the $20,000 of labor, so E is $82,000. Column G only rises by $20,000, from $80,000 to $100,000, because the gear was already billed as stored. After retainage, the line is worth $72,000 on pay application 3 and a further $18,000 on pay application 4.

Mistakes that cost money

  • Leaving installed material in column F as well as putting it in E. That bills it twice, and the GC is likely to send the application back.
  • Billing stored material without the backup. The GC can strike the line, and the money waits for next month’s application.
  • Storing off site without approval first. The GC can refuse to pay for it until it arrives.
  • Not billing it at all. You pay the supplier on its terms, often long before the item is set, and the gap is yours to fund.

Your subcontract decides what can be billed as stored and what proof is needed.

Questions

What people ask next.

Which column on the G703 is stored materials?

Column F, materials presently stored. It adds into column G, total completed and stored to date, which is D + E + F.

Can I bill for materials stored off site?

Often, yes, but usually only with the owner’s approval in advance. AIA A201 section 9.3.2 sets that condition, with procedures for title, insurance, storage and transport.

Is retainage held on stored materials?

Usually, yes. The G702 has a separate line, 5b, for retainage on stored material, and the contract sets the rate.

What happens to stored materials when they’re installed?

They come out of column F and go into column E for that period. Column G rises only by the new work, because the material was already billed.

What proof do GCs ask for with stored materials?

Usually the supplier’s invoice or a bill of sale, a certificate of insurance, dated photos and the storage location. Some also ask for a right to inspect or storage in a bonded warehouse.