What counts as stored materials?
Material bought for the job and not yet part of the work. For an electrical, mechanical or fire protection sub that’s usually the large, long lead items: switchgear, panels, light fixtures, air handlers, chillers, pipe and fittings, sprinkler heads.
Billing for them matters because you pay the supplier long before the item is set. Without a stored materials line, that cash sits with you until installation, sometimes for months.
Where do they go on the G703?
In column F. The continuation sheet has one row per line of the schedule of values, and these columns:
| Column | Heading | How it’s worked out |
|---|---|---|
| A | Item number | From the schedule of values |
| B | Description of work | From the schedule of values |
| C | Scheduled value | From the schedule of values |
| D | Work completed, from previous application | D + E from the last application |
| E | Work completed, this period | Installed this period |
| F | Materials presently stored | Stored now, not in D or E |
| G | Total completed and stored to date | D + E + F |
| % | Percent complete | G ÷ C |
| H | Balance to finish | C − G |
| I | Retainage | Used if the rate varies by line |
Column F is a snapshot of what’s stored now, so it isn’t carried forward from the last application. On the G702 summary page, retainage on stored material has its own line, 5b, worked out on the column F total, because some contracts hold a different rate on stored material.
What does a GC usually ask for?
The owner is paying for something that isn’t in the building yet, so the GC wants to know it exists, who owns it and that it’s protected.
- The supplier’s invoice, or a bill of sale that passes title to the owner.
- A certificate of insurance that covers the material where it’s stored and on the way to site.
- Dated photos of the material, tagged with the job name.
- The storage location: on site in a secure area, or the address of the warehouse.
- For material stored off site, the owner’s approval in advance. AIA A201 section 9.3.2 makes this a condition, with procedures for title, insurance, storage and transport.
Some contracts add more, such as storage in a bonded warehouse, a right to inspect, or a supplier lien waiver. Read the payment section of the subcontract and the prime contract’s terms that flow down to you.
A worked example
An electrical sub has a $180,000 line for switchgear and distribution, with 10% retainage. On pay application 3 it bills $18,000 of conduit rough in and $62,000 of switchgear delivered to a locked room on site. On pay application 4 the gear is set, and it bills $20,000 more labor.
| Column | Pay app 3 | Pay app 4 |
|---|---|---|
| C Scheduled value | 180,000 | 180,000 |
| D Previous | 0 | 18,000 |
| E This period | 18,000 | 82,000 |
| F Stored | 62,000 | 0 |
| G Total to date | 80,000 | 100,000 |
| % Complete | 44.4% | 55.6% |
| H Balance | 100,000 | 80,000 |
| Retainage at 10% | 8,000 | 10,000 |
On pay application 4, the $62,000 of gear leaves column F and goes into column E with the $20,000 of labor, so E is $82,000. Column G only rises by $20,000, from $80,000 to $100,000, because the gear was already billed as stored. After retainage, the line is worth $72,000 on pay application 3 and a further $18,000 on pay application 4.
Mistakes that cost money
- Leaving installed material in column F as well as putting it in E. That bills it twice, and the GC is likely to send the application back.
- Billing stored material without the backup. The GC can strike the line, and the money waits for next month’s application.
- Storing off site without approval first. The GC can refuse to pay for it until it arrives.
- Not billing it at all. You pay the supplier on its terms, often long before the item is set, and the gap is yours to fund.
Your subcontract decides what can be billed as stored and what proof is needed.