What is a back charge?
It’s the GC recovering a cost from you instead of paying it itself. The common ones on commercial jobs:
- Cleanup and debris removal the GC says you left behind.
- Damage to another trade’s work, such as a drywall patch after a late penetration.
- Correcting or finishing work the GC says was defective or incomplete.
- Labor the GC supplied when it says you fell behind schedule.
- Shared costs the subcontract assigns to subs, such as dumpsters or hoisting.
When can a GC back charge a sub?
When the subcontract gives it the right, and usually only after it follows the notice steps the subcontract sets. Standard forms build in a chance to cure before the GC steps in.
- The AIA’s standard subcontract, A401, requires written notice before the contractor supplies labor or materials and charges the cost to the sub. The number of days differs between editions.
- The ConsensusDocs 750 subcontract uses a two step notice to cure before the contractor can step in and charge the cost.
- Many contractors write their own subcontracts, with shorter notice or none. Read yours before the job starts.
A back charge should also be for a cost the GC actually incurred, and for work that was really in your scope.
Notice and documentation
The side with the better records usually wins. Keep these from the first day on site:
- Daily reports: who was on site, what got done and what was left clean.
- Dated photos of your work when it’s finished and before the next trade covers it.
- Every notice the GC sends, with the date you received it.
- Your reply to each notice, and what you did to fix the problem.
- Who else was working in the area, since damage is often another trade’s.
When the GC does charge you, ask for its backup: the notice, time sheets, invoices and photos of the work it did.
A worked example
A GC charges an electrical sub for cleanup on the third floor: two laborers for six hours at $65, a dumpster haul, and a 10% markup.
| Back charge 004 | Amount |
|---|---|
| Labor, 12 hours at $65 | 780.00 |
| Dumpster haul | 450.00 |
| Markup, 10% | 123.00 |
| Cleanup, third floor | 1,353.00 |
On pay application 6 the sub billed $62,000 of work with 10% retainage. The GC pays the earned amount less the back charge:
| Pay application 6 | Amount |
|---|---|
| Work completed this period | 62,000.00 |
| Less retainage, 10% | −6,200.00 |
| Less back charge 004 | −1,353.00 |
| Paid | 54,447.00 |
If the sub’s daily report and photos show the floor was left clean, it disputes all $1,353. If the notice came after the GC had already cleaned up, it disputes the markup and asks why it wasn’t given the chance to do the work itself.
How does a back charge show up on a pay application?
The AIA G702 has no line for back charges. A GC usually takes one in one of two ways: as a deduction from the payment it sends you, as in the example above, or as a deductive change order that lowers your contract sum.
Keep your own pay application clean either way. Bill the work you’ve completed against your schedule of values, and don’t reduce a line for a back charge you dispute. Track each back charge on its own list, with its amount, status and the payment it came off, so disputed money doesn’t disappear into a short payment.
How do you dispute a back charge?
- Reply in writing, inside the claim period in your subcontract. Some subcontracts bar a claim that isn’t raised in time.
- Ask for the backup: the notice, time sheets, invoices and photos.
- Check the steps. Was notice given, and were you given the chance to fix it first?
- Check the scope. Was the work yours, or another trade’s?
- Send your own records: daily reports, photos and any reply you already sent.
- Offer what’s fair. If part of it is yours, agree that part in writing and dispute the rest.
- Keep working while it’s settled, unless your lawyer tells you otherwise. Stopping work can put you in default.
State prompt payment laws can limit what a GC may withhold and may require it to say why in writing, and they vary by state and by public or private job.
This is general information, not legal advice. Your contract and state law decide.