What counts as a submittal?
The AIA’s general conditions, A201, name three kinds, and most specs follow the same split.
- Shop drawings: drawings, diagrams and schedules you prepare for this job, such as a sprinkler layout, a duct layout or a panel schedule.
- Product data: the manufacturer’s published cut sheets, ratings and dimensions for what you plan to install.
- Samples: a physical piece that sets the standard the finished work will be judged by, such as a device plate or a grille finish.
Submittals are not contract documents. They show how you intend to meet the contract, and an approval does not excuse a deviation you didn’t call out in writing when you sent it.
How does the review cycle work?
- You prepare the package and check it against the specs before it leaves your office.
- The GC reviews it, stamps it and sends it on. Under A201 the architect may return one the contractor hasn’t reviewed.
- The architect or engineer reviews it against the design and returns it with an action stamp.
- You order, fabricate or resubmit, depending on the stamp.
The stamps vary by firm, but the common set is approved (or no exceptions taken), approved as noted, revise and resubmit, and rejected. Approved as noted lets you proceed with the marked corrections, so read every note. A note can change a part number while the stamp still says approved.
How long does review take?
A201 asks the contractor to keep a submittal schedule and the architect to review in line with it, or with reasonable promptness when there isn’t one. Many specs set a number of days per review. Check your spec section on submittal procedures, then count each resubmittal as a full second cycle when you plan your orders.
Lead times decide the order
Work backwards from the day the equipment has to be on site. Review time, any resubmittal and the manufacturer’s lead time all sit in front of that date, and the manufacturer’s clock usually starts only when the order is released.
Send the long lead packages first: switchgear, transformers and generators, rooftop units and chillers. Equipment like this can take many months to arrive, and the order usually can’t be released until the submittal is back. Get the lead time from your supplier in writing on the day you price the job, because it can change between bid and buyout.
A sample submittal log
One line per package, from the day it’s required to the day it’s released for order. This is part of an electrical sub’s log.
| No. | Spec section | Item | Sent | Returned | Status | Need on site |
|---|---|---|---|---|---|---|
| 26 24 13-01 | 26 24 13 | Switchboard SB-1 | 3 Feb | 24 Feb | Approved as noted | 2 Jun |
| 26 24 16-01 | 26 24 16 | Panelboards | 3 Feb | 24 Feb | Revise and resubmit | 19 May |
| 26 24 16-02 | 26 24 16 | Panelboards, rev 1 | 3 Mar | With engineer | 19 May | |
| 26 51 00-01 | 26 51 00 | Light fixtures | 10 Feb | 3 Mar | Approved | 14 Jul |
| 26 27 26-01 | 26 27 26 | Wiring devices, sample | 17 Feb | With architect | 30 Jun |
The log should also carry who has the ball, the revision number, the date the order was released and the supplier’s promised ship date. Number resubmittals as revisions of the same package, so the history stays on one line of thought.
Mistakes that cost money
- Ordering before the submittal is returned. If it comes back rejected, the material is yours.
- Missing the notes on an approved as noted stamp, then installing what you submitted instead of what was marked.
- Substituting a product without saying so in writing. The approval won’t cover it.
- Sending long lead items late, then paying for overtime when the gear arrives after the ceiling is closed.
- Treating a review comment that adds scope as free. That’s a change, and it gets priced as one.
When a review comment adds work, write it up as a change order before you do it.
This is general information, not legal advice. Your contract and the project specs decide.