When should you write an RFI?
Write one when you can’t build from the documents without guessing. The AIA’s general conditions, A201, expect the contractor to study the drawings and report errors, inconsistencies and omissions it finds, so an RFI is also how you show you reported them.
- Two documents disagree: the electrical plan shows a 200A panel and the panel schedule says 225A.
- Something is missing: a unit is shown on the mechanical plan with no circuit on the electrical plan.
- The design won’t fit: a duct run clashes with a beam, or a sprinkler main can’t hold its elevation.
- A specified product is discontinued and you need a direction.
Don’t write one for an answer that’s already in the documents. Search the specs and the addenda first, because an RFI that points to a page you missed costs the GC’s goodwill.
What a good RFI contains
- A number, a short title and the date sent.
- The exact location: sheet, detail, grid line, room and spec section.
- One question, asked so it can be answered in a line.
- Your suggested answer, so the designer can just confirm it.
- Whether the answer could add cost or time, stated plainly.
- The date you need the answer by, tied to when the work is scheduled.
- Photos or a marked up sheet when they make the question clearer.
A sample RFI
| Field | Entry |
|---|---|
| RFI | E-014, Panel LP-2A rating |
| Sent | 6 Mar, to the GC’s project manager |
| Reference | Sheet E-201, grid C/4; panel schedule on E-601; spec 26 24 16 |
| Question | E-201 labels LP-2A as 200A. The schedule on E-601 shows a 225A main. Which rating governs? |
| Suggested answer | Use the 225A schedule rating and the feeder sized on E-601. |
| Impact | Possible added cost for a larger feeder. Price to follow if the answer differs from the bid documents. |
| Needed by | 20 Mar, so the panelboard submittal can go out |
The question fits on one line, the location can be found in seconds, and the cost warning is on the record from the first day.
What the RFI log tracks
One line per RFI, kept by your office, even when the GC keeps its own.
| RFI | Subject | Sent | Needed by | Answered | Cost or time | Change order |
|---|---|---|---|---|---|---|
| E-012 | Fire alarm device heights | 20 Feb | 1 Mar | 27 Feb | None | |
| E-013 | Missing circuit for RTU-3 | 28 Feb | 10 Mar | 9 Mar | Added cost | CO 007 |
| E-014 | Panel LP-2A rating | 6 Mar | 20 Mar | Possible |
Watch the gap between needed by and answered. A late answer that holds up your crew is a delay you may be able to claim, but only if the log shows when you asked and when you needed it.
How do RFIs turn into change orders?
An RFI answer is a clarification, and it doesn’t change the contract sum by itself. When the answer adds or changes work, price it and send a change order request that cites the RFI number, before you do the work.
In the log above, RFI E-013 found a rooftop unit with no circuit. The answer added a circuit, which went out as change order 007 with the RFI attached. See the change orders guide for how to price one.
Mistakes that cost money
- Building the extra work an answer asks for without pricing it first.
- Asking several questions in one RFI, then getting an answer to only one.
- Leaving out the needed by date, so a slow answer can’t be tied to the schedule.
- Taking a verbal answer in the field and never getting it in writing.
- Missing the notice deadline in your contract for claiming the added cost or time.
This is general information, not legal advice. Your contract and state law decide.