Requests for information (RFIs)

A request for information, or RFI, is a written question sent through the GC to the architect or engineer when the drawings and specs are unclear, conflict or leave something out. It gets you an answer on the record before you build, and when the answer adds work, it’s the paper trail behind your change order.

By Newlith  ·  Checked 27 Nov 2026
Asks
One question, in writing
Goes to
The architect or engineer, through the GC
Leads to
A change order when the answer adds work

When should you write an RFI?

Write one when you can’t build from the documents without guessing. The AIA’s general conditions, A201, expect the contractor to study the drawings and report errors, inconsistencies and omissions it finds, so an RFI is also how you show you reported them.

  • Two documents disagree: the electrical plan shows a 200A panel and the panel schedule says 225A.
  • Something is missing: a unit is shown on the mechanical plan with no circuit on the electrical plan.
  • The design won’t fit: a duct run clashes with a beam, or a sprinkler main can’t hold its elevation.
  • A specified product is discontinued and you need a direction.

Don’t write one for an answer that’s already in the documents. Search the specs and the addenda first, because an RFI that points to a page you missed costs the GC’s goodwill.

What a good RFI contains

  • A number, a short title and the date sent.
  • The exact location: sheet, detail, grid line, room and spec section.
  • One question, asked so it can be answered in a line.
  • Your suggested answer, so the designer can just confirm it.
  • Whether the answer could add cost or time, stated plainly.
  • The date you need the answer by, tied to when the work is scheduled.
  • Photos or a marked up sheet when they make the question clearer.

A sample RFI

FieldEntry
RFIE-014, Panel LP-2A rating
Sent6 Mar, to the GC’s project manager
ReferenceSheet E-201, grid C/4; panel schedule on E-601; spec 26 24 16
QuestionE-201 labels LP-2A as 200A. The schedule on E-601 shows a 225A main. Which rating governs?
Suggested answerUse the 225A schedule rating and the feeder sized on E-601.
ImpactPossible added cost for a larger feeder. Price to follow if the answer differs from the bid documents.
Needed by20 Mar, so the panelboard submittal can go out

The question fits on one line, the location can be found in seconds, and the cost warning is on the record from the first day.

What the RFI log tracks

One line per RFI, kept by your office, even when the GC keeps its own.

RFISubjectSentNeeded byAnsweredCost or timeChange order
E-012Fire alarm device heights20 Feb1 Mar27 FebNone
E-013Missing circuit for RTU-328 Feb10 Mar9 MarAdded costCO 007
E-014Panel LP-2A rating6 Mar20 MarPossible

Watch the gap between needed by and answered. A late answer that holds up your crew is a delay you may be able to claim, but only if the log shows when you asked and when you needed it.

How do RFIs turn into change orders?

An RFI answer is a clarification, and it doesn’t change the contract sum by itself. When the answer adds or changes work, price it and send a change order request that cites the RFI number, before you do the work.

In the log above, RFI E-013 found a rooftop unit with no circuit. The answer added a circuit, which went out as change order 007 with the RFI attached. See the change orders guide for how to price one.

Mistakes that cost money

  • Building the extra work an answer asks for without pricing it first.
  • Asking several questions in one RFI, then getting an answer to only one.
  • Leaving out the needed by date, so a slow answer can’t be tied to the schedule.
  • Taking a verbal answer in the field and never getting it in writing.
  • Missing the notice deadline in your contract for claiming the added cost or time.

This is general information, not legal advice. Your contract and state law decide.

Questions

What people ask next.

What does RFI stand for in construction?

RFI stands for request for information. It’s a written question to the design team about something in the drawings or specs that is unclear, conflicting or missing.

Who answers an RFI?

The architect or engineer of record usually answers it, and the GC passes it up and back down. A sub normally sends its RFIs to the GC, not to the designer directly.

Is an RFI answer a change order?

No. An answer clarifies the documents. If it adds or changes work, you still need a signed change order before that work changes the contract sum.

How long does the architect have to answer an RFI?

It depends on the contract and the project’s procedures, which often set a number of days. Put a needed by date on every RFI so a late answer can be tied to the schedule.

What is the difference between an RFI and a submittal?

An RFI asks a question about the design. A submittal shows the product or layout you plan to install and asks for it to be reviewed.

Should a sub suggest an answer in the RFI?

Yes, when you have one. A suggested answer is quicker to confirm than an open question, and it shows the designer you’ve read the documents.