When is work done on T&M?
When the scope can’t be priced up front: hidden conditions, extra work the general contractor needs today, or a change directive to proceed before the price is agreed. The subcontract usually says how T&M work is ordered, who can authorize it, and what rates apply. Read that section before the first ticket.
What must a T&M ticket carry?
- Job, date, and a ticket number that runs in order.
- Who asked for the work, and the change directive or reference it falls under.
- A plain description of the work and where it was done.
- Each worker by name and classification, with hours, split into straight time and overtime.
- Material, item by item with quantities, and equipment with hours or days.
- The printed name, signature and date of the person authorized to sign for the general contractor.
Why get it signed the same day?
A ticket signed today records hours the superintendent watched. A week later it’s an argument about memory. Some subcontracts require tickets to be handed in at the end of each workday, and some say unsigned tickets won’t be paid or that only a named representative, not a foreman, can sign.
Signing confirms the hours and material, not always the price. Price the ticket in the office from the contract rates, and send it back with the signed copy attached.
How is T&M work priced?
Labor is usually billed at the rates in the subcontract’s rate sheet, by classification, with overtime rates listed separately. Material is billed at invoice cost plus an agreed markup, and equipment at agreed rental rates. The markup and what it covers, overhead, profit or both, are set by the contract, so they vary from job to job.
A not to exceed cap sets the most you’ll be paid for the work. Track it as tickets come in, and tell the general contractor in writing before you reach it. On federal time and materials contracts, the FAR clause has the contractor notify the contracting officer when it expects charges over the next 30 days to take the total past 85% of the ceiling.
A worked example
One day’s ticket for extra conduit and receptacles, at a $95 journeyman rate, a $110 foreman rate and 15% markup on material.
| Ticket 014 | Amount |
|---|---|
| Journeyman, 12 hours at $95 | 1,140.00 |
| Foreman, 2 hours at $110 | 220.00 |
| Material at invoice cost | 380.00 |
| Material markup, 15% | 57.00 |
| Scissor lift, 1 day | 225.00 |
| Ticket total | 2,022.00 |
The work is capped at $5,000 not to exceed. Three tickets come in.
| Ticket | Amount | Left under cap |
|---|---|---|
| 014 | 2,022.00 | 2,978.00 |
| 015 | 1,486.50 | 1,491.50 |
| 016 | 1,180.00 | 311.50 |
| Total | 4,688.50 | 311.50 |
After ticket 015 more than half the cap is gone, which is the time to warn the general contractor and ask for the cap to be raised, not after the work runs past it.
How do tickets become a change order or invoice?
Gather the signed tickets for the work, price each one, and total them on one change order or T&M invoice with the tickets attached. On a job billed by pay application, the approved change order becomes a new line on the schedule of values and usually carries retainage like the rest.
- Submit monthly at the latest, so T&M lands on the next pay application.
- Keep a log: ticket number, date, signed or not, amount, and the change order it was billed on.
- Chase unsigned tickets the same week, while people remember the work.
Mistakes that cost money
- Tickets that pile up in the truck and get signed weeks later, or never.
- A signature from someone the subcontract doesn’t authorize.
- Running past a not to exceed cap without written approval.
- Mixing T&M hours into base contract cost codes, so they’re never billed.
This is general information, not legal advice. Your contract and the law of the state the job is in decide.