Job costing for subcontractors

Job costing is tracking every dollar of labor, material, equipment, subcontracts and job overhead against the job and the cost code it was estimated under. Comparing actual cost to the estimate each week, and forecasting the cost at completion, shows which jobs are making money while there’s still time to fix the ones that aren’t.

By Newlith  ·  Checked 27 Nov 2026
Cost types
Labor, material, equipment, subs, overhead
Compared against
The estimate, by cost code
Reviewed
Weekly, while the job runs

What are cost codes?

A cost code is a bucket the estimate and the actual costs share. Use the same codes in the estimate, on timecards and on purchase orders, or you’ll never line them up. Keep the list short enough that a foreman picks the right code without thinking.

  • By phase or area: rough in, trim, switchgear, fire alarm.
  • By cost type under each: labor, material, equipment, subcontract.
  • One code for job overhead: supervision, permits, temporary power, cleanup.

What goes into each cost type?

Labor is the biggest risk on most electrical, mechanical and fire protection jobs, and the easiest to undercount. Cost it at a burdened rate: the wage plus payroll taxes, workers’ compensation, insurance and benefits. A $42 wage that carries $20 an hour of burden costs you $62, and that’s the number to put against the job.

  • Material: from purchase orders and supplier invoices, coded when the order is placed, not when the bill is paid.
  • Equipment: rentals, and your own lifts and tools at an internal rate.
  • Subcontracts: committed value, then billed to date.
  • Job overhead: costs this job causes. Company overhead, like the office and the estimator, is usually covered by your markup instead.

A worked example

A $190,000 electrical fit-out, estimated at $158,400 of cost for a $31,600 margin. Labor is estimated at 1,200 hours at $62. At the weekly review, the foreman puts labor at 60% complete with 780 hours used.

Cost typeEstimateActual to dateForecast at completionVariance
Labor74,40048,36080,600(6,200)
Material52,00035,50054,000(2,000)
Equipment6,0004,2006,300(300)
Subcontract, low voltage18,0009,00018,0000
Job overhead8,0005,6008,0000
Total158,400102,660166,900(8,500)

Labor forecast: 48,360 ÷ 60% is 80,600. Another way to see it: 60% of 1,200 hours is 720 hours earned, but 780 were used, so the crew is 60 hours behind, $3,720 so far. Material forecast is what’s been bought plus the open purchase orders. The margin falls from $31,600, 16.6% of the contract, to $23,100, 12.2%.

What should you review every week?

  • Hours used against hours earned, by cost code. Labor overruns are cheapest to fix in the week they start.
  • Percent complete from the foreman, checked against what’s installed.
  • Open purchase orders and invoices not yet coded to a job.
  • Change order work: is it on its own code so it can be priced and billed?
  • Forecast at completion and the margin it leaves, against last week’s.

Mistakes that cost money

  • Costing labor at the bare wage. The job looks profitable until the burden lands in the company books.
  • Coding everything to one bucket. You know the job lost money, not where.
  • Waiting for the month end close. By the time a monthly report shows the overrun, the hours are spent.
  • Mixing change order work into base contract codes, so it’s never billed.
Questions

What people ask next.

What is job costing in construction?

Job costing tracks every cost of a job, labor, material, equipment, subcontracts and job overhead, against the job and the cost code it was estimated under. It shows whether each job is making the margin it was bid at.

What is a burdened labor rate?

It’s the wage plus everything that comes with it: payroll taxes, workers’ compensation, insurance and benefits. Job costs should use the burdened rate, because that’s what an hour of labor really costs the shop.

How many cost codes should a subcontractor use?

As few as will still tell you where a job lost money. Too many and foremen pick the wrong one; too few and every overrun lands in one bucket.

What is forecast at completion?

It’s what the job is expected to cost when it’s finished: cost to date plus the estimated cost to complete. Comparing it to the estimate shows the margin the job will really make.

How is job costing different from the WIP report?

Job costing works inside one job, cost code by cost code, usually weekly. The WIP report takes each job’s totals at month end and turns them into earned revenue and overbilling or underbilling.

Should company overhead be charged to jobs?

Costs a job causes, like supervision and permits, belong on the job. Company overhead, like the office and the estimator, is usually covered by the markup in the bid rather than charged line by line.