What are cost codes?
A cost code is a bucket the estimate and the actual costs share. Use the same codes in the estimate, on timecards and on purchase orders, or you’ll never line them up. Keep the list short enough that a foreman picks the right code without thinking.
- By phase or area: rough in, trim, switchgear, fire alarm.
- By cost type under each: labor, material, equipment, subcontract.
- One code for job overhead: supervision, permits, temporary power, cleanup.
What goes into each cost type?
Labor is the biggest risk on most electrical, mechanical and fire protection jobs, and the easiest to undercount. Cost it at a burdened rate: the wage plus payroll taxes, workers’ compensation, insurance and benefits. A $42 wage that carries $20 an hour of burden costs you $62, and that’s the number to put against the job.
- Material: from purchase orders and supplier invoices, coded when the order is placed, not when the bill is paid.
- Equipment: rentals, and your own lifts and tools at an internal rate.
- Subcontracts: committed value, then billed to date.
- Job overhead: costs this job causes. Company overhead, like the office and the estimator, is usually covered by your markup instead.
A worked example
A $190,000 electrical fit-out, estimated at $158,400 of cost for a $31,600 margin. Labor is estimated at 1,200 hours at $62. At the weekly review, the foreman puts labor at 60% complete with 780 hours used.
| Cost type | Estimate | Actual to date | Forecast at completion | Variance |
|---|---|---|---|---|
| Labor | 74,400 | 48,360 | 80,600 | (6,200) |
| Material | 52,000 | 35,500 | 54,000 | (2,000) |
| Equipment | 6,000 | 4,200 | 6,300 | (300) |
| Subcontract, low voltage | 18,000 | 9,000 | 18,000 | 0 |
| Job overhead | 8,000 | 5,600 | 8,000 | 0 |
| Total | 158,400 | 102,660 | 166,900 | (8,500) |
Labor forecast: 48,360 ÷ 60% is 80,600. Another way to see it: 60% of 1,200 hours is 720 hours earned, but 780 were used, so the crew is 60 hours behind, $3,720 so far. Material forecast is what’s been bought plus the open purchase orders. The margin falls from $31,600, 16.6% of the contract, to $23,100, 12.2%.
What should you review every week?
- Hours used against hours earned, by cost code. Labor overruns are cheapest to fix in the week they start.
- Percent complete from the foreman, checked against what’s installed.
- Open purchase orders and invoices not yet coded to a job.
- Change order work: is it on its own code so it can be priced and billed?
- Forecast at completion and the margin it leaves, against last week’s.
Mistakes that cost money
- Costing labor at the bare wage. The job looks profitable until the burden lands in the company books.
- Coding everything to one bucket. You know the job lost money, not where.
- Waiting for the month end close. By the time a monthly report shows the overrun, the hours are spent.
- Mixing change order work into base contract codes, so it’s never billed.