What does a WIP schedule show?
One line per open job, at a month end. Each line carries the same columns, so a job that’s slipping stands out against the rest.
- Contract value, including approved change orders.
- Estimated total cost, updated with your latest estimate to complete.
- Cost to date, from the job cost ledger.
- Percent complete, earned revenue and billed to date.
- Overbilled or underbilled, and the gross profit you now expect.
How is percent complete measured?
Most contractors use cost to cost: cost to date divided by estimated total cost. It’s an input method allowed under the revenue standard, ASC 606, for work done over time. It only works if the estimate is honest, because a cost estimate that’s too low makes the job look further along than it is.
Earned revenue is the contract value times that percentage. It’s what you’ve earned on paper, whatever you’ve billed.
A worked example
Three open jobs at month end.
| Job | Contract | Est. cost | Cost to date | Complete | Earned | Billed | Over (under) |
|---|---|---|---|---|---|---|---|
| School switchgear | 500,000 | 400,000 | 160,000 | 40% | 200,000 | 230,000 | 30,000 |
| Clinic fit-out | 300,000 | 255,000 | 204,000 | 80% | 240,000 | 210,000 | (30,000) |
| Warehouse lighting | 120,000 | 108,000 | 27,000 | 25% | 30,000 | 36,000 | 6,000 |
| Total | 920,000 | 763,000 | 391,000 | 470,000 | 476,000 | 6,000 |
The school job: 160,000 ÷ 400,000 is 40%, and 40% of 500,000 is 200,000 earned. You’ve billed 230,000, so it’s overbilled by 30,000. The clinic: 204,000 ÷ 255,000 is 80%, so 240,000 earned against 210,000 billed, underbilled by 30,000.
What do overbilling and underbilling mean?
Overbilling is billing ahead of the work. It shows on the balance sheet as a liability, billings in excess of costs and estimated earnings, because you still owe the work. A little is normal on the front of a job. A lot can mean cash from this job is paying for another.
Underbilling is work done and not yet billed. It shows as an asset, costs and estimated earnings in excess of billings. It can mean you’re slow to bill, or it can mean the cost estimate is too low and the job is losing money you haven’t seen yet. Lenders and sureties look hard at underbillings for that reason.
What happens when the estimate changes?
Say the clinic’s estimated cost rises from 255,000 to 270,000 with nothing else changed.
| Clinic fit-out | Before | After |
|---|---|---|
| Estimated cost | 255,000 | 270,000 |
| Percent complete | 80.0% | 75.6% |
| Earned revenue | 240,000 | 226,667 |
| Underbilled | 30,000 | 16,667 |
| Expected gross profit | 45,000 | 30,000 |
The underbilling shrinks and the profit you expect drops by 15,000. That’s profit fade, and the WIP is where it shows up first.
Mistakes that cost money
- Leaving the original estimate in place. If no one updates cost to complete, percent complete is wrong on every line.
- Leaving out approved change orders, or counting unapproved ones in the contract value.
- Booking costs late. A material invoice entered next month makes this month’s job look less complete than it is.
- Reading the total only. A net 6,000 overbilled can hide a 30,000 underbilling on one job.