The work in progress (WIP) schedule

A WIP schedule lists every open job with its contract value, estimated cost, cost to date and billings. Percent complete by cost turns those into earned revenue, and the gap between earned revenue and what you’ve billed shows whether each job is overbilled or underbilled. Banks and sureties read it to judge how your jobs are really going.

By Newlith  ·  Checked 27 Nov 2026
Percent complete
Cost to date ÷ estimated cost
Earned revenue
Contract × percent complete
Over or under
Billed less earned

What does a WIP schedule show?

One line per open job, at a month end. Each line carries the same columns, so a job that’s slipping stands out against the rest.

  • Contract value, including approved change orders.
  • Estimated total cost, updated with your latest estimate to complete.
  • Cost to date, from the job cost ledger.
  • Percent complete, earned revenue and billed to date.
  • Overbilled or underbilled, and the gross profit you now expect.

How is percent complete measured?

Most contractors use cost to cost: cost to date divided by estimated total cost. It’s an input method allowed under the revenue standard, ASC 606, for work done over time. It only works if the estimate is honest, because a cost estimate that’s too low makes the job look further along than it is.

Earned revenue is the contract value times that percentage. It’s what you’ve earned on paper, whatever you’ve billed.

A worked example

Three open jobs at month end.

JobContractEst. costCost to dateCompleteEarnedBilledOver (under)
School switchgear500,000400,000160,00040%200,000230,00030,000
Clinic fit-out300,000255,000204,00080%240,000210,000(30,000)
Warehouse lighting120,000108,00027,00025%30,00036,0006,000
Total920,000763,000391,000470,000476,0006,000

The school job: 160,000 ÷ 400,000 is 40%, and 40% of 500,000 is 200,000 earned. You’ve billed 230,000, so it’s overbilled by 30,000. The clinic: 204,000 ÷ 255,000 is 80%, so 240,000 earned against 210,000 billed, underbilled by 30,000.

What do overbilling and underbilling mean?

Overbilling is billing ahead of the work. It shows on the balance sheet as a liability, billings in excess of costs and estimated earnings, because you still owe the work. A little is normal on the front of a job. A lot can mean cash from this job is paying for another.

Underbilling is work done and not yet billed. It shows as an asset, costs and estimated earnings in excess of billings. It can mean you’re slow to bill, or it can mean the cost estimate is too low and the job is losing money you haven’t seen yet. Lenders and sureties look hard at underbillings for that reason.

What happens when the estimate changes?

Say the clinic’s estimated cost rises from 255,000 to 270,000 with nothing else changed.

Clinic fit-outBeforeAfter
Estimated cost255,000270,000
Percent complete80.0%75.6%
Earned revenue240,000226,667
Underbilled30,00016,667
Expected gross profit45,00030,000

The underbilling shrinks and the profit you expect drops by 15,000. That’s profit fade, and the WIP is where it shows up first.

Mistakes that cost money

  • Leaving the original estimate in place. If no one updates cost to complete, percent complete is wrong on every line.
  • Leaving out approved change orders, or counting unapproved ones in the contract value.
  • Booking costs late. A material invoice entered next month makes this month’s job look less complete than it is.
  • Reading the total only. A net 6,000 overbilled can hide a 30,000 underbilling on one job.
Questions

What people ask next.

What is a WIP report in construction?

A work in progress report lists every open job with contract value, estimated cost, cost to date and billings. It works out each job’s percent complete and earned revenue, and shows whether the job is overbilled or underbilled.

Is overbilling bad?

Not always. Some overbilling early in a job is normal and helps cash flow. Large or growing overbillings can mean the money is already spent elsewhere, leaving the end of the job short.

Why do banks and sureties care about underbilling?

Underbilling is revenue earned on paper that hasn’t been billed. If the cost estimate is too low, that revenue may never be collected, so large underbillings can be a sign of a losing job.

How often should a WIP schedule be updated?

Monthly is common, at the same time as the month end close and pay applications. Your bank or surety may also set its own schedule for receiving it.

Is cost to cost the only way to measure percent complete?

No. Some contractors measure units installed or labor hours instead. Cost to cost is the most common because the numbers already come from the job cost ledger.

What is profit fade?

Profit fade is the drop in a job’s expected gross profit between the bid and the finish. On a WIP schedule it shows when the estimated cost rises and earned revenue and margin fall.